Highway linking Oaxaca city and coast is 58% complete

Construction of a highway that will connect and drastically cut travel time between Oaxaca city and the coastal city of Puerto Escondido is currently 58% complete, according to state development bank Banobras.

Oaxaca Governor Alejandro Murat announced in February that the long overdue highway is on track to be completed in 2022.

The 6.8-billion-peso (US $280-million) Barranca Larga-Ventanilla highway will cut the 6 1/2-hour trip from the state capital to the popular surfing and beach destination to an estimated 2 1/2 hours.

The 104.2-kilometer route will connect Highway 175 at the town of Barranca Larga — a little over an hour south of Oaxaca city — with coastal Highway 200 in the municipality of Santa María Colotepec, just to the east of Puerto Escondido.

President López Obrador announced in June 2019 that the highway would finally see completion during his administration, as well as the similarly long overdue Mitla-Tehuantepec highway, in the east of the state. The projects floundered during previous administrations.

He toured the highway with Governor Murat earlier this month and said that Oaxaca was an example for the rest of the country in road construction.

“The construction workers in Oaxaca are the best in the world,” he said. “We’re building roads differently, not the conventional way, not how it was done before. We’re doing it with the participation of the people.”

In January, he visited Oaxaca communities to observe the results of a government program to give road investment money directly to communities in order to improve infrastructure. He called the road a “work of art” built by the people and “free of corruption.”

During his visit earlier this month, he said that his administration was able to make the investments happen as a result of its efforts to root out corruption in the government.

“That’s why we can have this budget without raising taxes or gas prices, without getting the country in debt,” he said.

The Barranca Larga-Ventanilla highway will have 10 bridges, a viaduct, three tunnels, nine junctions and two toll booths. In addition to tourism, it will benefit over 100,000 inhabitants of the region it traverses, as it will provide them with a faster way to get to the coast.

It is expected to see around 2,000 vehicles per day upon completion, and the speed limits will be set to 90-110 kilometers per hour.

Banobras said that the project will have generated 1,800 direct and 3,500 indirect jobs in the region.

Sources: Revista Transportes y Turismo (sp), Quadratin (sp)

Have something to say? Paid Subscribers get all access to make & read comments.
captured El Tanque

Iván Cazarín, regional CJNG boss known as ‘El Tanque,’ is captured in Zapopan

0
Cazarín is a major figure in the Jalisco New Generation Cartel and ran a major fuel theft operation in the states of Veracruz, Oaxaca, Tabasco and Puebla, though the charges could also include homicide, kidnapping, money laundering and drug trafficking.
workers on a construction project

Mexico’s fixed capital investment grew 6% in July, the fastest pace in 2 years

0
The overall FCI growth rate was up slightly from a 5.9% annual expansion in June, whereas annual private-sector FCI growth increased 2 percentage points from June to reach its highest level in 30 months, a sign that businesses' confidence in their long-term economic prospects is improving.
grandmother tree in Lochiel, Arizona

Activists condemn felling of ancient trees for border wall

0
Federal contractors felled a centuries-old cottonwood on the U.S.-Mexico border Monday after U.S. Border Patrol agents removed protesters who had spent about 70 days trying to save it from President Donald Trump’s border wall expansion.
BETA Version - Powered by Perplexity